
Click to see the September 2025 update.

East addition stairwell progress, with CMU work complete and crews installing the mechanical room. (September 2025)
The north wall section removed has been filled with CMU blocks, and facade brick will be added to match the existing exterior. (September 2025)
View from the basement level looking up into the west mechanical room addition. (September 2025)
Progress on subgrade preparations for the northeast parking lot. (September 2025)
See the August 2025 update.
See the July 2025 update.
Click to see the June 2025 update.
Click to see the May 2025 update.
Click to see the April 2025 update.
See the March 2025 update.
See January/February 2025 update.
See December 2024 update.
See November 2024 update.
See October 2024 update.
See September 2024 update.