Old Main Monthly Update.jpg

Click to see the September 2025 update.

east addition.jpg

East addition stairwell progress, with CMU work complete and crews installing the mechanical room. (September 2025)

north wall.jpg

The north wall section removed has been filled with CMU blocks, and facade brick will be added to match the existing exterior. (September 2025)

basement looking up.jpg

View from the basement level looking up into the west mechanical room addition. (September 2025)

subgrade.jpg

Progress on subgrade preparations for the northeast parking lot. (September 2025)

blog divider.jpg

See the August 2025 update.

See the July 2025 update.

Click to see the June 2025 update.

Click to see the May 2025 update.

Click to see the April 2025 update.

See the March 2025 update.

See January/February 2025 update.

See December 2024 update.

See November 2024 update.

See October 2024 update.

See September 2024 update.

Renovation Photos June 2025

First Floor Elevator.jpg

First Floor (June 2025): Structural steel upgrades. 

Second Floor 2.jpg

Second Floor (June 2025): Structural steel upgrades.

Third Floor 2.jpg

Third Floor (June 2025). Structural steel upgrades.

Fourth Floor.jpg

Fourth Floor (June 2025): Wood framing, floor system framing, structural modifications.

blog divider.jpg